Cooperation with DTEK company
This year, DTEK, in addition to scheduled annual repairs at thermal power plants, was forced to carry out additional repairs to restore damaged infrastructure as a result of the destruction received during the war.
Concern "SouzEnergo" mobilized all production reserves to manufacture the necessary spare parts for thermal power plants of DTEK in the shortest possible time.
We repaired 14 chimney wheels K-31.5 for Ladyzhynska TPP, 4 chimney wheels K-31.5 for Kryvorizhska TPP, 2 mill fan wheels VM-20 for Prydniprovska TPP, and 4 mill fan wheels VM-20 for Kurakhivska TPP. Complete sets of spare parts for SHBM (armor, fasteners and parts of the moving part of the mill) were also delivered.
In total, since the beginning of the military invasion, 820 tons of armor have been manufactured and delivered for the needs of the Kurakhivska, Burshtynska and Ladyzhynska TPPs.